We were nearing the end of a months-long painting and decorating project in collaboration with William MacDonald, a Toronto-based interior designer, when I got an email from the owners.
“We’re selling the place – can you help us get a few things in order around the house?”
The client’s real estate agent recommended a cosmetic renovation of the master bathroom to help fetch a higher price on the market. As luck would have it, the home they’d always wanted practically fell into their lap — and so they decided to sell this one.
I believe the eagerness to have us take on a major renovation on such short notice was largely due to our proven track record of beating milestones and handling small, random jobs along the way. We were always the “yes” team. If there was a leaky faucet, a creaking stair tread, or a new light fixture to hang, my response was always the same:
“Give me a couple days and I’ll get back to you with a plan and pricing.”
-
In just three weeks, we completed the full scope of renovations in this bathroom:
Selective demolition of existing slate tiles and other pre-identified elements
Installation of Schluter DITRA Radiant Floor System
Supplied and installed new gypsum board (drywall) and CGC Mould Tough drywall in wet areas
Waterproofed shower walls with Schluter KERDI membrane
Installed Anatolia Statuario honeycomb tiles on the shower base
Installed Anatolia Carrara Nevosco 12” x 12” tiles on the shower walls and curb
Installed full-height, half-panel shower glass
Prepared wall and ceiling surfaces and completed all painting
Trim-out Electrical: outlets, switches, Schluter radiant floor thermostat, wall sconces, pot lights
Trim-out Plumbing: new shower drain, shower head, valves, faucets, pedestal sink, and toilet
Finish Carpentry: re-mounted doors and hardware, installed supply registers, mounted mirrors
-